Oh no! I have hours on Team System Tasks but No Baseline!
I ran across an interesting issue recently and I wanted to share the solution.á I am currently working on a fairly large project.á We have had a turbulent start and I was not able to baseline my project plan before my developers began working on their tasks.á I knew that from a schedule standpoint we were hosed, but other Earned Value calculations should still be ok.á I baselined my project plan but discovered an issue.á When I refereshed my project plan from TFS, all of the baselines were wiped ......

Posted On Wednesday, September 27, 2006 9:09 PM

Oh no! I have hours on Team System Tasks but No Baseline!
I ran across an interesting issue recently and I wanted to share the solution.á I am currently working on a fairly large project.á We have had a turbulent start and I was not able to baseline my project plan before my developers began working on their tasks.á I knew that from a schedule standpoint we were hosed, but other Earned Value calculations should still be ok.á I baselined my project plan but discovered an issue.á When I refreshed my project plan from TFS, all of the baselines were wiped out ......

Posted On Wednesday, September 27, 2006 8:09 PM