Geeks With Blogs
Robert's Sysadmin Blog Unraveling the datacenter one fibre at a time June 2008 Entries
Version 7.1 of the TCR rack diagram
This is more or less how its gonna be. All the bits are now in place, half the rack stuff has been put in place already, the last stuff goes in coming Vriday. One of the biggest oversights we made was with power requirements. If you want redundant power for a lot of servers, you need to make sure you have a LOT of plugs, enough PDU’s, and plenty of PSU to back it all up. We didnt, partly due to time contraints, budget, but also short-sightedness, and my reliance on people that I, to put it bluntly, ......

Posted On Monday, June 30, 2008 11:57 PM

Computer Room Cleanup and re-cabling Pics and Movies
So a few weeks ago, we spent our Saterday doing major recable work on the new Technical Computer room (TCR) in the new location, in preperation for our Big Bang services move coming up on the 5th of July (it was delayed from the 22nd)) So thise pics and videos are a few weeks old now, but who cares. PICTURES (scroll down for movies) Not enough room to neatly get all the fat KVM cables sorted, so later I actually extended the room for the cables to 2U, and used the cable guide rail only for ethernet ......

Posted On Monday, June 30, 2008 11:37 PM

Copyright © Robert Kloosterhuis | Powered by: GeeksWithBlogs.net | Join free